CASE STUDY · AVIATION · IT & PMO
An aviation organisation moved its IT and PMO departments off spreadsheets and email into one ClickUp workspace. 140 to 160 people across 20 teams, delivered on time and within budget.
The client is not named. Workspace screens on this page are recreated with sample data.
01Who they are
The organisation runs its technology through two departments: IT, made up of 20 teams of seven or eight people each, and a Project Management Office that oversees delivery. Together that is 140 to 160 people, all working on projects, tickets and operational activity at the same time.
02Where they started
Before ClickUp, both departments ran on manual processes. Work lived in Excel files that were emailed around, so each team ended up with its own copy and nobody could be sure which one was current. As the organisation grew, keeping up took more of everyone’s time.
| Department: Information Technology | Airline Operations Support | Version: 14 | Last updated: see cell N1 (manually) | |||||||||
| NOTE: PLEASE SAVE YOUR OWN COPY BEFORE EDITING | |||||||||
| Ticket # | Date Raised | Raised By | Dept | Issue Description | Assigned To | Priority | Status | SLA Met? | Comments / Follow-up |
|---|---|---|---|---|---|---|---|---|---|
| TK-001 | 02/01/2026 | Mohammed Al-Ghamdi | Ground Ops | Check-in system frozen at Terminal B counters | Khalid Farhan | HIGH | RESOLVED | Y | Restarted application server. |
| TK-002 | 02/01/2026 | Sara Al-Otaibi | Finance | SAP login not working after password reset | Nora Hassan | HIGH | Resolved | N | SLA breach – took 2 days |
| TK-003 | 05/01/2026 | Faisal Al-Zahrani | Flight Ops | Crew scheduling module showing wrong rosters | Ahmad Saeed | URGENT | IN PROGRESS | Waiting for vendor patch – emailed | |
| TK-004 | January 6 | Hessa Al-Mutairi | HR | Unable to access shared drive – permissions | Tariq Mahmoud | Medium | resolved | Y | Permissions updated in AD group. |
| TK-005 | 06/01/2026 | Unknown | ??? | Printer not working near boarding gate C12 | Maintenance? | low | OPEN | Is this even IT? Or facilities? | |
| TK-006 | 07/01/2026 | Reem Al-Dosari | Cargo | Barcode scanners not reading at cargo bay 3 | Khalid Farhan | HIGH | OPEN | Khalid said he’d look at it | |
| TK-007 | 07/01/2026 | Omar Al-Shehri | IT | VPN disconnecting every 30 mins for remote staff | Ahmad Saeed | HIGH | In progress | Checked firewall logs. Still investigating. | |
| TK-009 | 8-Jan | Fahad Al-Qahtani | Finance | Excel file corrupted – monthly payroll data | Nora Hassan | URGENT | RESOLVED | N | Recovered from backup. Backup was 2 days old. |
1Version 14, with a note asking everyone to save their own copy.
2One status, three spellings: RESOLVED, Resolved, resolved.
3Three date formats in one column.
4A ticket with no owner and no department.
A tracker like the one the teams used, recreated with sample data.
Excel was the main project management tool.
Teams worked on different versions of the same file.
Updates and requests travelled by email.
Assignments, statuses and reports were done by hand.
Leadership had little view of progress, workload or bottlenecks.
Working across teams was slow, with tools that did not connect.
03What we built
After comparing project management platforms, the organisation chose ClickUp as its central work management tool. We set the workspace up to follow the way the departments are already organised, so every team could find its own work and leadership could see all of it.
One for each department, including IT and the PMO.
One for each of the 20 IT teams, so every team runs its own work.
Projects, workflows and day-to-day operations inside each Folder.
Each ticket or piece of work, with an owner, status and deadline.
The IT Service Desk shows how it comes together. Requests arrive through an intake form, move across a board with custom statuses, carry the fields that matter for each ticket and roll up into a dashboard for leadership.
Use this form to report an IT issue, ask for technical support or submit a service request. Fill in every required field so your ticket reaches the right team.
Submit| Name | Priority | Ticket type | Affected system | SLA deadline |
|---|---|---|---|---|
| VPN Client Connection Failure – Remote Staff | Urgent | Project Task | Network | 14/08/26 |
| Barcode Scanner Not Recognised – Baggage Check-in | High | Incident | Hardware | 16/09/26 |
| Name | Priority | Ticket type | Affected system | SLA deadline |
|---|---|---|---|---|
| Email Sync Failure – Operations Department | High | Bug / Maintenance | Application | 29/07/26 |
| Name | Priority | Ticket type | Affected system | SLA deadline |
|---|---|---|---|---|
| ERP Login Failure – Post Password Change | High | Bug / Maintenance | ERP | 01/09/26 |
| Software Licence Request – Adobe CC x20 | Normal | Project Task | Application | 08/07/26 |
| Name | Priority | Ticket type | Affected system | SLA deadline |
|---|---|---|---|---|
| Printer Offline – Floor 3 | Normal | Incident | Hardware | 07/07/26 |
This dashboard gives IT leadership one live view of every open ticket in the Service Desk: where demand is rising, what is being worked on and whether issues are resolved within the agreed service levels.
It is built for managing service ahead of problems, not reacting to them.
Recreated with sample data. Switch tabs to see each view.
The organisation needed one system that could handle many teams, projects and reports at once. ClickUp’s hierarchy of Spaces, Folders, Lists and Tasks matched the way the departments already worked.
04How the team adopted it
The biggest challenge was not the technology.It was change management.
Teams were used to their spreadsheets and inboxes. Moving 20 of them to one central platform took careful planning, regular training and support that continued well past launch.
Sessions that brought each team into the new workspace.
Regular training for users across all 20 teams.
Support for users throughout the transition period.
05What changed
The rollout was delivered on time and within budget, and both departments saw the difference. With manual steps removed and every project in one place, teams turned work around significantly faster.
Up to 50% faster turnaround time
employees onboarded
IT teams in one platform
and within the approved budget
06Lessons learned
As requirements change, keep stakeholders informed about the resources being used and the effect on the timeline. Early communication avoids surprises later.
Test workflows, automations, permissions and reporting before launch. Issues found early make the rollout smoother and give users confidence in the new system.
Adoption is not only about software. Training, communication and engagement decide whether a transformation works.
A large, complex organisation replaced spreadsheets, email and manual reporting with one platform. More than 20 teams now spend less time on administration and more on delivering results.
How a hospital’s 100-person PMO replaced Excel files and email threads with one ClickUp workspace.