Agree on go/no-go criteria early
Rollout expectations, adoption requirements and the final decision process belong in discovery, not at the end.
CASE STUDY · GAMING & ESPORTS · PMO
A gaming and esports organisation wanted its PMO to run every project from the first business case to completion. Dtech designed a connected ClickUp system for approvals, projects, partnerships, reporting and audit follow-up.
The client is not named. Workspace screens on this page are recreated with sample data, and the budget figure is illustrative.
01Who they are
The client is a gaming and esports organisation. Its Project Management Office wanted a structured way to take projects from the initial business case through to completion, to collect performance metrics from departments, and to give leadership one place to see projects and the wider portfolio.
Submission and multi-level approval
Linked to the approved business case
Local and international intake
Weekly and monthly department metrics
One view for leadership
Organised and followed up
Assigned to management and executives
The seven connected workflows the PMO asked for.
02Where they started
The PMO needed more than a basic project tool. Proposals, approvals, execution and completion lived in separate steps. Reporting was the heaviest load: one team member collected weekly and monthly metrics from many departments, followed up with each team and rebuilt everything into PowerPoint presentations for leadership.
1One person chasing every department for weekly and monthly numbers.
2Figures arriving late, by email, in different formats.
3All of it rebuilt by hand into a PowerPoint for leadership.
A reporting cycle like the PMO’s, recreated with sample data.
Manage business cases and approvals across departments.
Connect approved business cases to project execution.
Track projects through to completion.
Simplify weekly and monthly reporting.
Give leadership a consolidated view.
Manage audit findings and executive actions in one place.
03What we built
Dtech started with partnership intake and departmental reporting. As requirements developed, the scope grew into a broader PMO solution that connects business case approvals, project management, portfolio tracking, audit findings and leadership action items.
Departments submit business cases through a form. Each one moves through the review stages it needs, up to the CEO when the approval threshold requires it. Once approved and closed, the workflow can create the linked project automatically, with the business case kept as the reference.
| Project | Business case | Department | Status |
|---|---|---|---|
| Regional tournament series | BC-024 | Events | IN PROGRESS |
| Creator partnership programme | BC-019 | Partnerships | IN PROGRESS |
| Arena fan app refresh | BC-015 | Digital | IN REVIEW |
| Grassroots league pilot | BC-011 | Community | COMPLETE |
Each project keeps a link back to the business case that approved it.
Stage names are illustrative. The local route included stages for Saudi requirements.
Each department submits its numbers here once a week. Monthly metrics use a second form.
Submit| Finding or action | Owner | Severity | Status |
|---|---|---|---|
| Vendor contracts missing sign-off dates | Finance | High | Open |
| Event insurance renewals not tracked | Operations | Medium | In progress |
| Access reviews overdue for two systems | IT | High | In progress |
| Board action: refresh sponsorship policy | Chief of Staff | Normal | Done |
Sample findings. Actions assigned to management and executive stakeholders sit in the same place.
Recreated with sample data. Switch tabs to see each view.
04How the team adopted it
Implementation and adoptionare two different milestones.
The organisation preferred to evaluate the PMO system as one complete package rather than introduce workflows one phase at a time. At the latest project review, it had not yet confirmed whether it would go ahead with ClickUp, so improvements in reporting time or productivity have not been established.
Tried different access levels and workspace structures to fit each reviewer.
Implemented several reporting requirements; some advanced dashboard needs remained platform limits.
Designed, configured, tested and demonstrated every workflow together.
05What changed
Dtech completed substantial design, configuration, testing and demonstration work across the PMO workflows. The result showed how these processes can work together in one ClickUp environment.
designed and configured
from sponsor to CEO
local and international
months, in multiple phases
The client has not yet confirmed adoption, so reporting efficiency, time savings and productivity gains have not been established.
06Lessons learned
Rollout expectations, adoption requirements and the final decision process belong in discovery, not at the end.
Knowing the requirements is only half the job. How the organisation plans to roll out matters as much.
This client wanted to evaluate the whole system at once. That changes how and when value can be shown.
A well-structured PMO needs connected processes, not separate trackers. Dtech designed and configured one ClickUp environment for proposals, approvals, execution and reporting, and learned to treat implementation and adoption as separate parts of the work.
How a steel and construction group brought CRM, sales and project delivery for two businesses into one ClickUp workspace.
BOOK THE FIRST HOUR
As a ClickUp Diamond Partner, we are measured on real adoption, not hours billed. If the first session works, your team will ask for more. If it does not, we stop there.
Book a Free Hour